To all our Valued Customers
Please find the attached update – current shipping terminal situation in Australia
In Summary:
SYDNEY DPW
Based on the outcome of a Protected Action Ballot Order (PABO) last week, the
Maritime Union of Australia (MUA) can now undertake work bans and stoppages
within 5 working days of notice provided to DPW.
At this time, however, the MUA have not tendered notice to DPW.
As such, no change where Protected Industrial Action (PIA) remains lifted for
Fremantle, Brisbane and Melbourne, but where work restrictions still apply for
Sydney, and berthing protocols continue until the PIA has been lifted.
Average delays in Sydney DPW now stand at 24 to 72 hours
Congestion due to the number of off-window vessels, impacting the berthing line-up.
Expected recovery now estimated by week 40, but remaining under close review.
PATRICK
Delays in Sydney now averaging between 12-14 days for the current week
The situation may unfortunately deteriorate further depending on the impact of PIA.
The already announced port omissions should help to improve the vessel line-up, however this area also remains under close review.
Please feel free to contact your Customer Solutions Representative, should you have any queries or concerns.